Toronto Hydro-Electric System Public Infrastructure Engineering Vulnerability Assessment Pilot Case Study

Toronto Hydro-Electric System Public Infrastructure Engineering Vulnerability Assessment Pilot Case Study

Thus, the objective of this pilot case study is to evaluate the vulnerability of selected THESL distribution
infrastructure to current climate, using the Protocol, Steps 1 to 3, to structure the evaluation. The infrastructure
components selected by THESL for this project are seven feeder systems from three sub-stations:
 Area A Station: Three 27.6 kV feeders: A-1, A-2 and A-3;
 Area B Station: Two 13.8 kV feeders: B-1; B-2;
 Area C Station: Two 13.8 kV feeders: C-1; C-2.